NEXT STEPS
Q3 2020
Completion and occupation of YOND.01
Q4 2020
‘Best architects’ gold award in the commercial and industrial buildings category
Q2 2021
City of Zurich Good Buildings award (for 2016–2020)
Q4 2024
Receipt of the legally valid building permit for the expansion of the YOND campus
Q1 2025
Connection to the district heating network as part of the campus’s sustainable energy supply
Q2 2025
Start of construction for the new buildings YOND.02, YOND.03 and YOND.04
Q4 2026
YOND.04 building/external work completion dates
Q3 2028
YOND.02 and YOND.03 building/external work completion dates
Q4 2028
Gradual entry into operation of new buildings